Sutton Estate Chelsea

Chelsea, London

The Sutton Dwellings, Chelsea has offered social rented homes in the heart of some of Europe's most expensive real estate for over a century. Four blocks have been completely remodelled. The original 181 homes, many of them bedsits and all of them falling well short of modern standards, have become 89 1, 2 and 3 bedroomed properties.

Four blocks have been completely remodelled: the original 181 homes, many of them bedsits, have become 89 one, two and three bedroomed properties.

ClientClarion Housing
DeveloperDurkan
ArchitectsHTA
Resident engagement platformEbrik Standard Package
Open the live resident site

Construction progress

All video content was captured and produced by Ebrik's team of videographers.

Complete
Refurbishment progress100%

The videos and information below are only a short overview of the actual platform, to view all the information go to the live platform.

  1. Step 1Complete

    Demolition / Strip out

    From site

    InteriorAugust 2022

    Before work can commence on the new project, the site is made safe. Trained professionals locate and make safe any power, water, gas and waste services, and the strip-out begins.

    AboutAugust 2022

    The removal of interior walls, floors, ceilings and pipework clears the way for the refurbishment to begin.

  2. Step 2Complete

    Roof works

    From site

    Site tourMay 2023

    The existing roof is removed to make way for new joists and rafters, the first step in the block's new roofscape.

    Roof tilesMay 2023

    With the structure complete, the new tiles go on and the roof becomes weathertight.

  3. Step 3Complete

    Internal structure

    From site

    Site tourAugust 2023

    Falsework goes in to support the structure while new steel supports are installed and the lift shafts are built.

  4. Step 4Complete

    External facade

    From site

    Guided tourJuly 2023

    New external windows and doors transform the look of the block from the street, before the scaffold comes down.

  5. Step 5Complete

    Internal fit-out

    From site

    Site tourJune 2023

    First fix plumbing and electrics run through the building, wiring the new homes from the inside.

    Site tourMay 2024

    Decoration completes the internal fit-out, and the homes are ready for handover.

  6. Step 6Complete

    External works

    From site

    Site tourAugust 2024

    All that remains now is to open up the site and tidy the grounds, with hard and soft landscaping bringing greenery to the grounds.

    DroneAugust 2024

    A drone view over the finished grounds, with new lighting pedestals and ground source heat pumps installed.

  7. Step 7Complete

    Build complete

    From site

    Site tourJuly 2024

    Testing, commissioning and snagging sign off the finished homes before the first handovers.